Phase II: Cottonwood Dr and Adjacent Cul de Sacs

Improvements

Improvements to Cottonwood Drive and the adjacent cul de sacs include:

  • Reconstructing the roads
  • Improving the drainage
  • Replacing the sidewalks and curb ramps to meet ADA standards
  • Installing street lights to meet current standards

Schedule

August – September 2020 Field Survey
September – December 2020 Preliminary Design
Early January 2021 Project Open House
January 13, 2021, Wed., 4-8 pm Project One-on-One Meetings / Open House
Ike “Woody” Woodman Recreation Center
January – February 2021 Final Plans, Specifications, and Estimate
March 2021 Advertise & Bid Project for Construction
Summer 2021 Construction

Open House January 8-12, 2021

Click HERE to see the information that was presesnted at the Online Open House.

 

Public Input

The project team wants to hear from you! Your feedback and comments are welcome at any time. We have several ways you can comment:

Mail

Write

  • Write us a letter or give us a call. See our contact information below.

Also, be sure to sign up to be on the email list to receive periodic project updates.
Sign Up For Project Email Updates

Contacts

Tobias Lockhart, PE
Senior Civil Engineer
DOWL
9085 Glacier Highway
Juneau, AK 99801
(907) 209-4232
tlockhart@dowl.com

Brad Sontag
City of Valdez Project Manager
PO Box 307
Valdez, AK 99686
(907) 835-5478, Ext 8
bsontag@ValdezAK.Gov